At the NCRA Board of Directors meeting today, NCRA will be presented with an estimate to repair the rail line from Windsor to Redwood Valley, which is North of Ukiah.  In the report, NCRA will be presented with four different scenarios, and will decide which repair scenario is the most economical for them to proceed with.

  1. Windsor - Redwood Valley (59.4 miles)
    1. Estimated Cost from NWP - $20.7 million
    2. Repairs line to North end of siding, MP 122.3
      1. Replace 52,004 ties
      2. Repair/Replace 52 bridges, 326 culverts, 5 tunnels, 27 crossing surfaces, & 23 grade crossing warning systems
      3. Assumes repairing grade crossing warning systems, not replacing them.
  2. Windsor - Ukiah (52 miles)
    1. Estimated Cost from AndersonPenna Partners - $45.8 million
    2. Repairs line to central Ukiah
    3. Assumes replacing all grade crossing warning systems, not repairing them.
  3. Windsor - Cloverdale (27.7 miles)
    1. Estimated Cost from NWP - $5.1 million
    2. Repairs line to south end of Cloverdale tunnel, MP 85.6
      1. Replace 12,258 ties
      2. Repair/Replace 24 bridges, 94 culverts, 0 tunnels, 16 crossing surfaces, & 8 grade crossing warning systems
      3. Assumes repairing grade crossing warning systems, not replacing them.
  4. Cloverdale - Redwood Valley (36.7 miles)
    1. Estimated Cost from NWP - $15.6 million
    2. Repairs line from South end of Cloverdale tunnel to North end of Siding, MP 122.3
      1. Replace 39,746 ties (estimated)
      2. Repair/Replace 28 bridges, 232 culverts, 5 tunnels, 11 crossing Surfaces, & 15 grade crossing warning systems
      3. Assumes repairing grade crossing warning systems, not replacing them.

 

It looks like they are going to try for option 3, which is repairing the line to Cloverdale (apx. $5 million).  A more detailed repair analysis can be seen here:  http://northcoastrailroad.org/Agendas/2014/20140312/Item_F.2_031214...

Just thought I'd post this for everyone, in case they hadn't seen it yet.

James Bradley, Jr.

Oakley, CA

Views: 1166

Comment

You need to be a member of Northwestern Pacific Railroad Network to add comments!

Join Northwestern Pacific Railroad Network

Comment by Mike Cook on March 26, 2014 at 1:42am

I just sent off an email to Doug McCorkle at the NCRA, I'll pass along any info I get from him.

Comment by Mike Cook on March 20, 2014 at 11:48pm

Not yet Dan, we should know more soon :) Get the line open to at least Ukiah, and preferably to Redwood Valley asap, they need this area to get their revenue up.

Comment by Don Pogue on March 14, 2014 at 5:50pm

Does anyone know the outcome of the meeting?

Comment by Carl O'Connor on March 13, 2014 at 7:16pm
Politics it is it tell you politics!!! You will probably find out that PG&E supports friends of the eel river. Wouldn't supprise me. Maybe pg&e could start using their spur in sr to receive poles and transformers again.
Comment by Mike Davis on March 13, 2014 at 6:50pm

the pipeline itself wasn't the issue, it was a PG&E easement regarding the pipleine that created the issue. The spur itself wouldn't have gone anywhere near the pipeline. (I think I heard that PG&E's refusal to the spur was some residual paranoia coming from San Bruno)

Comment by Carl O'Connor on March 13, 2014 at 6:38pm
Richard. I don't see that happening because how would pg&e be able to service the pipeline if they needed to??
Comment by Don Pogue on March 13, 2014 at 5:28pm

Whatever happened with the possible new spur for Alexander Valley Cellars in Windsor?  Did that whole possibility get shut down because of PG&E?

Comment by Jordan on March 13, 2014 at 5:19pm

The thing is, the Lombard facility is already used by Sonoma and Mendo wineries. I don't see them bum rushing towards a new one just because it's a few miles closer.

Comment by Emilio Galo on March 13, 2014 at 4:17pm

Thats pretty expensive to repair. I am looking foward to seeing this railroad operating daily like it did back then. 

http://http://www.railpictures.net/photo/452377/

Comment by Tommy Tommy on March 12, 2014 at 10:01pm

Would NWP be able to provide that kind of service to Sonoma and Mendo winemakers? 

© 2019   Created by Mark Drury.   Powered by

Badges  |  Report an Issue  |  Terms of Service